When is Site Plan approval required?

All commercial/industrial, institutional or multi-family construction projects will require Site Plan approval from the Town of Plympton Planning Board in addition to the above-described procedure. Applications for Site Plan Review are available in the Planning Board Office. All construction plans will be required to be certified by a Structural Engineer certified by the Commonwealth of Massachusetts. All construction over 35,000 cubic feet, or at the discretion of the Building Inspector, will require plan certification by a Design Architect and Engineer certified by the Commonwealth of Massachusetts. Periodic site inspections and certification of all construction by the engineer are required to be provided to the Building Inspector. You should consult with the Building Inspector regarding additional fees required for plan review by a Structural Engineer for the Building Inspector.

AttachmentSize
PDF icon When is a Site Plan Review required?293.75 KB